Smart Building – Industrial Power Units for Industry, LLC | Saudi Arabia https://www.ipu-sa.com Powering Progress with Excellence Mon, 12 May 2025 23:50:17 +0000 en-US hourly 1 https://wordpress.org/?v=6.9.4 https://www.ipu-sa.com/wp-content/uploads/2025/04/cropped-IPU-Site-Logo-scaled-2-32x32.png Smart Building – Industrial Power Units for Industry, LLC | Saudi Arabia https://www.ipu-sa.com 32 32 King Salman Park – TSE and HVAC Control Systems https://www.ipu-sa.com/king-salman-park-tse-and-hvac-control-systems/ Thu, 01 Aug 2024 08:59:57 +0000 https://www.ipu-sa.com/?p=6330 ...]]>
King Salman Park – TSE & HVAC Control Systems

Powering environmental infrastructure in the world’s largest urban park.

 

Project Overview
King Salman Park is one of Riyadh’s flagship Vision 2030 projects — set to become the world’s largest urban park. As part of two separate packages within the development, IPU SA was contracted to supply intelligent Motor Control Centers (MCCs) and custom HVAC control panels for both Treated Sewage Effluent (TSE) Package 3 and Buildings A & B of the park’s Phase I development.

 

Clients & Partners

  • Clients: WETICO, Energy Concept

  • Location: Riyadh, Saudi Arabia

  • Completion: Q4 2024

  • Technology Partners: Siemens, Schneider Electric

 

Products & Solutions Provided

TSE Package 3:

  • Motor Control Centers (MCCs)

  • Siemens PLCs with HMI

  • Skid-mounted containerized control units

Buildings A & B:

  • AHU & Fan Control Panels

  • Schneider VFDs

  • DOL starters with remote monitoring

  • Building-integrated HVAC automation

 

Technical Highlights

Component

Description

TSE System

30,000 m³/day capacity with packaged MCC units

PLC

Siemens PLC with HMI for TSE process visualization

HVAC Panels

Supplied and commissioned for air handling units in two major park buildings

Drives

Schneider VFDs for fan and pump efficiency

Installation

Containerized MCCs and building-mounted panel layouts

 

Challenges & IPU SA Solutions

Challenge

IPU SA Solution

Rapid deployment required for phased park infrastructure

Pre-fabricated, containerized MCCs

Multi-vendor coordination across large site

Modular panel systems and flexible integration logic

High HVAC load diversity across buildings

Customized control panels with VFDs and expansion options

 

Key Outcome

  • Seamless control of TSE infrastructure and HVAC distribution

  • Improved energy efficiency and operational responsiveness

  • Scalable control logic for future expansions

  • Fully commissioned on-time with operator interface support

  • Environmentally aligned with Vision 2030 sustainability goals

 

Project Media

]]>
6330
Al Rajhi Bank – ATS, MDB, and DC System Integration https://www.ipu-sa.com/al-rajhi-bank-ats-mdb-and-dc-system-integration/ Sun, 01 Oct 2023 08:59:47 +0000 https://www.ipu-sa.com/?p=6504 ...]]>
Al Rajhi Bank – ATS, MDB, and DC System Integration

Secure power infrastructure for one of the world’s largest Islamic banks.

 

Project Overview
Al Rajhi Bank, a major force in Saudi Arabia’s financial sector, required a robust and uninterrupted power distribution system to support its growing operational footprint. IPU SA was contracted to supply, install, and test an integrated power system consisting of Automatic Transfer Switches (ATS), Main Distribution Boards (MDBs), and a DC system — designed to support continuous banking operations and IT infrastructure.

 

Clients & Partners

  • Client: Global Infrastructure Modules

  • Location: Riyadh, Saudi Arabia

  • Completion: October 2023

  • End-User: Al Rajhi Bank

 

Products & Solutions Provided

  • ATS Panels for automatic source switching

  • LV Main Distribution Boards (MDBs)

  • DC Backup Power System for sensitive IT equipment

  • Protection and metering integration

  • Installation, testing, and handover documentation

 

Technical Highlights

Component

Description

ATS Panels

Automatic source selection between utility and generator

MDBs

LV boards with segregated loads and surge protection

DC System

Supports uninterrupted power for data and security layers

Wiring

Professionally labeled and routed for fast maintenance

Monitoring

Optional remote diagnostics integrated via Modbus

 

Challenges & IPU SA Solutions

Challenge

IPU SA Solution

High sensitivity to downtime in banking operations

Redundant source switching and controlled ATS delay logic

Compliance with banking security & electrical audit standards

Delivered IEC 61439-certified equipment with full documentation

Limited space for board layout

Custom compact MDB design with bottom-entry cabling

 

Key Outcome

  • Reliable dual-source power with automated failover

  • Full support for security and financial data operations

  • Compact, organized power room layout

  • Reduced maintenance time through labeled design and digital wiring maps

  • Delivered within timeline and aligned with Al Rajhi’s audit standards

 

Project Media

]]>
6504
NEOM Hospital – MV Synchronization Control System https://www.ipu-sa.com/neom-hospital-mv-synchronization-control-system/ Wed, 01 Mar 2023 08:59:47 +0000 https://www.ipu-sa.com/?p=6417 ...]]>
NEOM Hospital – MV Synchronization Control System

Smart energy control for the Kingdom’s most futuristic healthcare facility.

 

Project Overview
The NEOM Hospital represents a bold step in the future of healthcare in Saudi Arabia — integrating cutting-edge technology, sustainability, and patient-centered design. As part of this next-generation medical infrastructure, IPU SAdelivered a customized MV Synchronization Control System to manage power from 14 generators and 3 bus couplers, ensuring reliable and redundant electricity for the hospital’s operations.

 

Clients & Partners

  • Client: Double Vision

  • Location: NEOM, Saudi Arabia

  • Completion: March 2023

  • Technology Partner: ComAp

 

Products & Solutions Provided

  • MV Synchronization Control Panels

  • Standalone SCADA System for remote monitoring

  • ComAp InteliGen & InteliNeo 6000 controllers

  • Generator control, bus coupler logic, and protection relays

  • Load sharing, sequencing, and auto-transfer systems

 

Technical Highlights

Component

Description

Generators

14 MV generators coordinated with 3 bus couplers

Controllers

ComAp InteliNeo 6000 with load sharing logic

SCADA

Standalone interface for full system diagnostics

Design

Fully redundant with failover protection

Integration

Configured to meet NEOM’s future-readiness and quality benchmarks

 

Challenges & IPU SA Solutions

Challenge

IPU SA Solution

Large number of distributed MV generators

Designed and tested central control logic with high-speed synchronization

Strict reliability and performance criteria

Integrated top-tier ComAp controllers with intelligent sequencing

Social and technological commitment expectations

Delivered a future-proof solution fully aligned with NEOM’s sustainability and resilience goals

 

Key Outcome

  • Seamless synchronization of complex MV power system

  • Redundant control across all generators and bus couplers

  • Compliant with NEOM’s high-availability and ESG requirements

  • Optimized SCADA for maintenance and energy tracking

  • Delivered on time with fully documented commissioning

 

Project Media

]]>
6417
Sindalah Island – Fuel Control and SCADA System https://www.ipu-sa.com/sindalah-island-fuel-control-and-scada-system/ Wed, 01 Feb 2023 08:59:35 +0000 https://www.ipu-sa.com/?p=6516 ...]]>
Sindalah Island – Fuel Control & SCADA System

Smart fuel management for a self-sustained luxury island destination.

 

Project Overview
Sindalah Island, one of the flagship destinations of NEOM, is a high-profile luxury development located on the Red Sea. Operating entirely on off-grid generation, it requires an exceptionally reliable fuel management and power control system. IPU SA was selected to engineer and commission a fully redundant PLC-based fuel control system integrated with a custom SCADA platform to monitor, report, and manage power distribution across the island’s critical infrastructure.

 

Clients & Partners

  • Client: Integrated Engineering Contracting Co.

  • Location: Sindalah Island, Tabuk Province, Saudi Arabia

  • Completion: February 2023

  • End-User: NEOM

 

Products & Solutions Provided

  • Schneider Electric Programmable Logic Controllers (PLCs)

  • SCADA System for centralized monitoring and alerts

  • Fuel distribution and level management logic

  • Generator fuel supply control and failover programming

  • Field device integration and I/O mapping for remote diagnostics

  • Redundant architecture for critical applications

 

Technical Highlights

Component

Description

Fuel System

Full island power generation dependent on diesel supply

Control Architecture

Redundant PLC with watchdog and override protection

SCADA

Customized user interface for real-time fuel status, alarms, and event history

Integration

Field sensors, valves, and pumps connected via digital and analog I/O

Reporting

SCADA logging, fault alerts, and preventive maintenance tracking

 

Challenges & IPU SA Solutions

Challenge

IPU SA Solution

Zero tolerance for fuel-related power interruption

Dual-controller redundancy with system watchdog

Harsh environmental exposure

IP-rated enclosures and marine-grade connectors

Real-time visibility across multiple field components

Custom SCADA with multi-tiered alert logic and HMI interface

 

Key Outcome

  • Fully automated fuel control supporting uninterrupted power

  • Remote visibility and alert system to prevent manual monitoring

  • Reduced operator risk and improved maintenance scheduling

  • Island-wide power stability supporting high-end hospitality infrastructure

  • Delivered on schedule with FAT and SAT completed

 

Project Media

]]>
6516
Maraya, Ashar Valley – MV Synchronization and Reactor System https://www.ipu-sa.com/maraya-ashar-valley-mv-synchronization-and-reactor-system/ Thu, 01 Dec 2022 08:59:14 +0000 https://www.ipu-sa.com/?p=6435 ...]]>
Maraya, Ashar Valley – MV Synchronization & Reactor Control System

Powering the world’s largest mirrored structure with smart control and stability.

 

Project Overview
Maraya, located in AlUla’s Ashar Valley, is a globally recognized architectural marvel and the largest mirrored building in the world. As a high-profile venue for concerts, events, and cultural gatherings, uninterrupted power and electrical stability are mission-critical. IPU SA was contracted to engineer and commission a custom MV Synchronization Control System that also manages shunt reactor logic to mitigate high capacitive reactance caused by the site’s extensive cabling.

 

Clients & Partners

  • Client: NESMA & Partners

  • Location: AlUla, Saudi Arabia

  • Completion: December 2022

  • Technology Partners: Schneider Electric, ComAp

 

Products & Solutions Provided

  • MV Synchronization Control Panels

  • MV Generator Control Integration

  • Reactive Power Compensation Logic

  • ComAp-based control for shunt reactors

  • Load balancing and power quality stabilization

  • Local and remote HMI for real-time operations

 

Technical Highlights

Component

Description

Network Complexity

High-reactance due to long cable runs

Reactor Control

Intelligent management of shut reactors via PLC/SCADA logic

Power Coordination

Synchronization of MV generators for load distribution

Stability

Protection logic to prevent system failure under harmonic stress

Operator Interface

Real-time diagnostics via SCADA and touchscreen HMI

 

Challenges & IPU SA Solutions

Challenge

IPU SA Solution

Excessive capacitive reactance from large cable network

Installed and programmed shunt reactor control for compensation

Risk of generator capacitor failure under reactive loads

Dynamic logic to adjust for live harmonic and load shifts

High sensitivity to downtime during events

Redundant control and protection layers for guaranteed uptime

 

Key Outcome

  • Optimized generator performance through reactive power control

  • Enhanced system stability despite complex cabling layout

  • Zero performance degradation under full load conditions

  • Delivered system meets Maraya’s world-class infrastructure standards

  • Reduced operational risk for public events and exhibitions

 

]]>
6435