Automation, Energy, Featured, Infrastructure, Project, Utility

NEOM Construction Village – MV Synchronization and Solar Control System

NEOM Construction Village – MV Synchronization & Solar Control System

Hybrid power for Saudi Arabia’s largest workforce infrastructure.

 

Project Overview
As part of the early-phase development of NEOM, the 5K and 10K Construction Villages serve as the first operational hubs for housing and supporting the labor force that will build the city of the future. IPU SA was selected to engineer, supply, and commission an integrated MV Synchronization Control System and Solar Control System that collectively manage 14 MV generators, 3 bus couplers, and nearly 3 MVA of solar power across both sites.

 

Clients & Partners

  • Client: NESMA

  • Location: NEOM, Saudi Arabia

  • Completion: January 2024

  • Technology Partner: ComAp

 

Products & Solutions Provided

Automation & Control:

  • MV Synchronization Control Panels

  • ComAp InteliNeo 6000 Controllers

  • Generator and bus coupler load management

  • Real-time SCADA integration

Renewable Energy Integration:

  • Solar Control Panel Systems

  • Hybrid logic for generator + solar load optimization

  • PV monitoring, isolation, and failover systems

 

Technical Highlights

Component

Description

Generators

14 MV gensets coordinated with 3 bus couplers

Solar System

Nearly 3 MVA of PV power integrated into hybrid controller

Controllers

ComAp InteliNeo with SCADA-based logic

Hybrid Logic

Load-sharing between solar and diesel to reduce fuel costs

Monitoring

Web-based and local SCADA visualization with alarm management

 

Challenges & IPU SA Solutions

Challenge

IPU SA Solution

Coordination between renewable and diesel systems

Delivered intelligent hybrid logic with PV prioritization

Massive generator network requiring redundancy

Deployed a fully redundant sync system with backup controllers

Fast-paced timeline for NEOM operational readiness

Parallel design + build execution with phased commissioning

 

Key Outcome

  • Seamless hybrid power control across 2 construction villages

  • Fuel savings through optimized PV integration

  • Real-time visibility and diagnostics across generator fleet

  • Aligned with NEOM’s sustainability and digitalization standards

  • Delivered ahead of milestone deadlines

 

Project Media

Privacy Settings
We use cookies to enhance your experience while using our website. If you are using our Services via a browser you can restrict, block or remove cookies through your web browser settings. We also use content and scripts from third parties that may use tracking technologies. You can selectively provide your consent below to allow such third party embeds. For complete information about the cookies we use, data we collect and how we process them, please check our Privacy Policy
Youtube
Consent to display content from - Youtube
Vimeo
Consent to display content from - Vimeo
Google Maps
Consent to display content from - Google
Spotify
Consent to display content from - Spotify
Sound Cloud
Consent to display content from - Sound
Cart Overview